DIN 69901-5:2009-1
We need some definitions first:
- Mitwirken: Collaborate: The project manager coordinates other planners, collects their work, makes his own analysis of it, and present them to the investor.
- Erstellen/Aufstellen: Create: it is about preparing reports on state of works.
- Abstimmen: Coordinate: Submitting the work of other planners to the investor, looking for the agreement from the client for implementation.
- Umsetzen: Convert: Coordinate the planning process, information and decisions system, and check their compliance.
- Fortschreiben: update: follow through that all partners have always the last versions of documents.
- Prüfen: Check: you need to check the plans, documentation, but also the invoices from planners and other involved parties.
- Überprüfen: Verify: controlling of finished phases, results, to the released status. You don’t need to control the details, just the completeness, plausibility, consistency of the documents.
- Analysieren und bewerten: Analyse and evaluate: take some samples to check if the planners are doing their work correctly.
- Steuern: Control: influence all active in the project to go into the right direction with the project.
2.1 Preparing the project
2.1.1 Organisation, information, coordination, and documentation tasks
- Develop the organisational structure, coordinate and document it.
- Coordinate the planning for the planning.
- Help define the project goals and the documentation of the project specifications
- Coordinate the communication structure and reporting system.
- Define the decision management system.
- Define the change management system.
- Contribute to the risk management system.
- Participate in the selection of a project communication system.
- (Coordinate specific internal units of the client.)
- (Prepare templates for reporting to the client.)
- (Setting up your own project communication system)
- (Prepare the organizational basis for multiple projects/programs/portfolios)
- (Design, prepare and align risk management systems.)
- (Plan regulatory approval procedures.)
- (Communication with the affected third parties and the relevant public.)
2.1.2 Qualities and quantities
- Verify the existing basis (Grundlagen) of planning requirements.
- Collaborate at the clarification of site issues: procurement, documentation.
- Review the results of the baseline investigation (Grundlagenermittlung).
- (Create and coordinate the needs plan.)
- (Inquiry regarding the infrastructure and obtain the relevant and documents.)
- (Prepare and conduct the architectural competition.)
- (Structure the processes for sustainability strategy.)
2.1.3 Costs and financing
- Preparation of the cost framework for investment and usage.
- Definition of investment and funding.
- Review the contract proposals of planers and other participants.
- Set up the project specific cost tracking.
- (Create feasibility studies.)
- (Use client-supplied computer programs for the documentation.)
2.1.4 Deadlines, capacities and logistics
- Set up and adjust the project timeframe.
- Controlling timeframe for the entire project and the capacity framework.
- Logistical factors taking into account relevant location and boundary conditions.
2.1.5 Contracts and insurances
- Preparation of a delivery (Vergabe) and contract structure for the entire project.
- Prepare and coordinate the contents of the planner contracts.
- Selection of the contractors, negotiations and preparations of the assignments.
- Propose the contract dates and deadlines for the planner contracts.
- Insurance concept for the entire project.
2.2 Planning
2.2.1 Organisation, information, coordination, and documentation tasks
- Update the project specific organizational specifications.
- Analyze and evaluate the planning processes for conformity of the project goals.
- Update the documentation of the project specifications.
- Verify the communication structure – reporting to the client.
- Convert decision management.
- Convert change management.
- Analyze and Evaluating the coordination services of the planners.
- Collaborate in risk management.
- Evaluate the proper use of the communication system by the stakeholders.
- Collaborate at the regulatory approval.
- (Represent the planning concept to the public)
- (Operate your own project communication system.)
- (Implement risk management systems with special requirements.)
- (Involvement of participating third parties and the public in the project.)
2.2.2 Qualities and quantities
- Ongoing analysis and evaluation of the performance of the participants.
- Controlling the planning of the sampling.
- Control the result documentation of the participants.
- (Control the sustainability certification processes.)
- (Control planning with 3D modelling processing and BIM.)
2.2.3 Costs and financing
- verify the costs estimation and calculation and add corrections.
- Cost control to meet the cost targets.
- Budgeting and cash outflow.
- Review and release proposals regarding the invoices.
- Update the project-specific cost tracking (continuous).
- (cost estimate/calculation according to DIN 276.)
- (usage costs estimate/calculation and usage cost control.)
- (profitability calculations.)
- (value engineering, cost effectiveness, contracting ability, sustainability, energy consumption, material suitability, logistics, workflow.)
2.2.4 Deadlines, capacities and logistics
- Updating the time frame.
- Verify the schedule of the planning participants.
- Update of the time frame.
- Schedule the planning, with analysis and evaluation of the scheduling updates.
- Update the logistical variables.
- Set up the schedule for the integration of strategic facility management.
- (Schedule for planning and construction.)
- (Schedule of the deadlines for planners.)
- (Create a logistics concept.)
- (Match logistics measures with neighboring and neighborhood interests.)
2.2.5 Contracts and insurances
- Contribute to the enforcement of contractual obligations to the parties.
- Implement the insurance concept for all project participants.
2.3 Preparing for execution
2.3.1 Organisation, information, coordination, and documentation tasks
- Update the organization with project structure planning.
- Analyze the planning processes for conformity with the project goals.
- Update the documentation of the project specifications.
- Verify the communication structure – reporting to the client.
- Implement decision management.
- Implement change management.
- Analyze and evaluate the coordination services of the object planner.
- Contribute to risk management.
- Evaluate the proper use of the communication system by the stakeholders.
- (Operate your own project communication system.)
- (Implement risk management systems with special requirements.)
- (Involvement of participating third parties and the public in the project.)
2.3.2 Qualities and quantities
- Ongoing evaluation of the planning results with the specified project goals.
- Bid evaluations and procurement proposals prepared by the plan participants.
- Examine the effects of offers for compliance with the specified project objectives..
- Participate in the required sampling.
- (Send the tender documents.)
- (Controll the sustainability and certification processes.)
2.3.3 Costs and financing
- Verify the target values from planners on the current cost calculation.
- Review the cost calculations made by the planners on price specifications.
- Review the bid evaluations for the reasonableness of the prices.
- Specify the cover confirmations for orders.
- Cost control of the offer tests and cost comparisons of the planning participants.
- Review and release proposals of invoices for participants for payment.
- Plan funding and outflow.
- Update the project-specific cost tracking (continuous).
- (Create profitability calculations.)
2.3.4 Deadlines, capacities and logistics
- Update the time frame.
- Verify the planning of the contracting parties for planning.
- Update of the control schedule with input from planners.
- Verify the available offers with regard to specified dates.
- Schedule control with target/actual comparisons regarding execution planning.
- Update and test the development of logistical parameters.
- (Update the scheduling for planning and construction.)
- (Create time schedule for (Vergabe).)
- (Continue the alignment of logistical measures with neighboring and neighborhood interests.)
2.3.5 Contracts and insurances
- Contribute to the enforcement of contractual obligations to the parties.
- Contribute to the structuring of the (vergabe) procedure.
- Verify the contract documents for completeness and plausibility.
- Participate in the contract negotiations until the time of signature.
- Specify the contractual dates and deadlines for the contract of execution.
- (Participate in the selection, procurement, construction and implementation of special information systems (eg for facility management))
2.4 Execution
2.4.1 Organisation, information, coordination, and documentation tasks
- Update the organizational specifications with project structure planning.
- Evaluate the planning processes for conformity with the given project goals.
- Update the documentation of the project specifications.
- Verify the communication structure – reporting to the client.
- Implement decision management.
- Implement change management.
- Analyze and evaluate the coordination services of object monitoring.
- Contribute to risk management.
- Evaluate the proper use of the communication system by the stakeholders.
- Assist the client in the initiation of independent proceedings.
- (Coordinate special requirements of the operator / user organization.)
- (Operate your own project communication system.)
- (Organizational and construction support in court proceedings.)
- (Implement risk management systems with special requirements.)
- (Contribute to the involvement of third parties involved and the public in the further project realization.)
2.4.2 Qualities and quantities
- Evaluate the services of object monitoring, suggest adaptation measures.
- Locally verify of the services of the object monitoring.
- (Controll the sustainability and certification processes.)
2.4.3 Costs and financing
- Cost control to meet the cost targets.
- Verify and release proposals for invoices of plan participants for payment.
- Invoice verification of the object monitoring for payment to contractors.
- Specification of cover confirmations for supplements.
- Updating the planning on funds requirement and outflow.
- Updating the project-specific cost tracking (continuous).
- (Verify the invoices of the executing companies.)
2.4.4 Deadlines, capacities and logistics
- Updating the time frame.
- Verify the schedule of the planners, compliance with the schedule.
- Update control schedules, inclusive the schedule of the planning participants.
- Schedule the execution taking into account the project monitoring services.
- (Create a detailed commissioning plan integrating all project participants including users.)
2.4.5 Contracts and insurances
- Contribute to the enforcement of contractual obligations to the parties
- Help client in averting claims of third parties (neighbors, citizens’ initiatives).
- Examination of the object surveillance and participation in the commissioning.
- Participation in the acceptance preparation.
- (Coordinate the insurance-relevant claims settlement.)
2.5 Finishing the project
2.5.1 Organisation, information, coordination, and documentation tasks
- Collaborate in the transfer/takeover/commissioning/use.
- Systematic archiving of project documentation.
- Verify the compilation of documentation by the planning participants.
- Verify the communication structure – reporting to the client.
- Complete decision-making / change and risk management.
- Organize the completion of the project communication system.
- (Organizational and building support in court proceedings.)
- (Organize the completion of your own project communication system.)
- (Complete the risk management system with special requirements.)
- (Verify the project documentation of the experts involved.)
2.5.2 Qualities and quantities
- Analyze and evaluate the list of limitation periods for claims for defects.
- (Initiate, coordinate and control the repair of defects.)
- (Controll the sustainability and certification processes.)
2.5.3 Costs and financing
- Verify the cost determination of the object and specialist planner.
- Verify the invoices of the project participants for payment.
- Verify the audit of the object monitoring for payment to contractors.
- Verify the services of the plan participants in the release of security deposits.
- Complete the project-specific cost tracking.
- (Create the usage manuals)
2.5.4 Deadlines, capacities and logistics
- Control of commissioning, acceptance (Abnahme) and delivery.
2.5.5 Contracts and insurances
- Contribute to the legal acceptance (Abnahme) of planning services.